Planned Works Programme

Last updated: 16 Jun, 2022 02:45pm

Current Works

This page includes details of planned work in Carterton District.

  • Ruamāhanga Roads forward works programme
  • Other works

Ruamāhanga Roads forward works programme

Drainage renewals: Belvedere Road
  • Stretch of footpath on Mckenzie Terrace to receive maintenance during May 2022. Location: 200A to 210 Belvedere Road
  • Work: Drainage Renewal
  • Estimated date: May 2022
  • Duration: +- 4 weeks

 

Footpath renewals: McKenzie Terrace
  • Stretch of footpath on Mckenzie Terrace to receive maintenance during May 2022.Location: McKenzie Terrace form Pembroke st. to Broadway (Western side)
  • Work: Footpath renewals:
  • Estimated date: May 2022
  • Duration: +- 4 weeks

Other works

Wastewater: Dalefield Road

Dalefield Road

What

  • Wastewater [ from State Highway 2 to the Dalefield Wastewater Treatment Plant]
  • Water supply pipes start early July [from new water tanks to Lincoln Road]

When

  • May to July 2022.

Where

  • Dalefield Road onto State Highway 2 closed.
  • Detours in place.
  • Speed warnings will be in place along SH2.